Commercial & office moving in Denver.
Workstation-by-workstation planning, careful IT handling and after-hours scheduling, so your team is back to work on the first day.
Scope an office move by workstation
An office move is a set of small moves that have to finish together. The cleanest way to scope it is by workstation, not by square foot. Count desks, chairs, filing units, monitors and personal items for each person, then add shared spaces: conference rooms, break rooms, server closets and storage.
That count turns into labor hours, crate quantities and truck loads. It also gives the office manager a way to assign each person a crate number and a destination desk, which is the single biggest factor in a fast Monday morning.
| Item | What to count | Why it matters |
|---|---|---|
| Workstations | Desks, chairs, pedestal drawers | Sets crew size and total hours |
| Shared furniture | Conference tables, couches, lockers | Often needs disassembly and a larger truck |
| IT and AV | Servers, switches, displays, phones | Needs labeling and a power-down plan |
| Records | Filing cabinets and boxes | Heavy, and sometimes confidential |
| Special items | Safes, lab gear, kitchen equipment | Needs specific handling and sometimes a vendor |
After-hours and weekend scheduling
Most offices cannot stop working for a day. The usual answer is to move on a Friday evening or over a weekend, with a Monday morning go-live. After-hours moves often mean more coordination with building management, security and elevators, and sometimes a premium on labor.
The fastest way to lose a weekend is to learn on Friday that the freight elevator is not available until Saturday at noon. Ask the building manager for freight elevator hours, loading dock rules and any required paperwork at least two weeks ahead.
IT equipment and the Monday test
The IT plan decides whether Monday works. Servers, switches and phone systems need a documented shutdown order, labeled cabling and a restart order that someone has written down and tested. Workstations are simpler: label each cable bundle with the person and the desk, and photograph the setup.
- Back up before anything moves, and verify the backup restores.
- Label every device and every cable end with matching tags.
- Pack monitors upright in dedicated cartons or padded crates.
- Move network core equipment last and set it up first.
- Schedule a smoke test with a handful of users before the full go-live.
Phase the move to protect the business
For larger offices, a single move night may be too much. Phasing lets one team move while another keeps working. The trade-off is a longer project and two sets of logistics.
Your team is under 30 people
Move in a single weekend with labeled crates
Your team is 30 to 150 people
Move by department in two or three waves
You have a server room or lab
Move that space on its own plan with its own vendor
Your lease ends before the new space is ready
Ask about short-term storage and delayed delivery
You are consolidating two offices
Inventory and cull before anything is packed
A planning timeline
| When | What happens |
|---|---|
| 8 weeks out | Confirm lease dates, request estimates, reserve freight elevators |
| 6 weeks out | Walkthrough, inventory, crate quantities, floor plan for the new space |
| 4 weeks out | Staff communication, crate delivery, IT plan finalized |
| 2 weeks out | Building paperwork, parking and loading plan, vendor schedule |
| Move week | Staff pack personal items, final inventory, backups verified |
| Move night | Load, transport, place, IT restart |
| Monday | Smoke test, punch list, crate pickup |
The bottom line
What planning saves
A labeled inventory and a tested IT restart cut the time to a working Monday.
Destination tags and floor plans avoid moving the same crate twice.
Building rules and insurance paperwork handled early prevent weekend surprises.
Send your headcount and the addresses through the quote form, or run a rough number in the estimator using the office option.
At a glance
Offices, clinics, studios and small to mid-size teams
Workstations, labor hours, equipment and scheduling
Weekday, evening or weekend